Retention Storm Water Pond C-2

Client Charlotte County
Location Midway Boulevard
Scope Of Work New Four Lane Roadway
Schedule 2015-2018
Engineer Giffels-Webster Engineers, Inc.

Project Detail

CONSTRUCTION PROGRESS: 05/24/18 – The construction crews have cleared stormwater pond “C-2” of large vegetation, and have installed a primary stormwater outfall running to the Yale Waterway.